FY 2008-2009 PLANNING/BUDGETING CALENDAR
|
|
Date: |
Planning Event: |
OCTOBER
|
|
5-Oct |
Staff Employee Evaluation Forms sent out by Human
Resources. |
| |
NOVEMBER
|
| 16-Nov |
Staff Employee Evaluation Forms
due to Human Resources. |
| |
| Late November |
Job Reclassification Requests sent out by Human
Resources. |
| |
DECEMBER
|
|
Early December |
Enrollment Projections Meeting to be attended by Sr
Director for Student Services, Provost and VP for
Academic Affairs, and VP for Administration and Finance. |
| |
| 5-Dec |
President completes prioritization of University
strategies. |
| |
| 14-Dec |
“FY 09 Planning/Budget Instructions” updated on Budget
website. |
| |
December 14 -
Jan. 29 |
Units prepare FY 09 budget requests, communicating with
faculty/staff and other units affected. |
| |
| 17-Dec |
Proposed Budgets for Sugar Land and Cinco Ranch due to
Budget Office. |
| |
| 19-Dec |
Job Reclassification Requests
due to Human Resources. |
| |
JANUARY
|
| January |
UHV Tuition and Fee
Forums. |
| |
| January 29-30 |
Budget Committee conducts “Budget Hearings.”
Cabinet-level supervisor brings his/her component’s FY 09 annual plan and budget
requests forward. Department heads may be requested by
cabinet level supervisors to attend. |
| |
|
FEBRUARY
|
| 25-Feb |
Tuition and Fee changes due to System to be presented at
the board meeting. |
|
|
|
MARCH
|
| 10-Mar |
Board of Regents approval of Tuition and Fees. |
| |
|
|
Early March |
Budget guideline details from System (endowment income
estimates, investment income estimates, debt service,
service charges, etc). |
|
|
| Early March |
Budget Committee tentatively finalizes the FY 09 budget. |
| |
|
Early March |
FY 09 Merit Recommendation Form to department heads (if
merit funding is available). |
| |
|
Mid-March |
Distribute FY 09 budget information to the Cabinet-level
supervisor who may request reconsideration in accordance
with stated procedures. |
| |
|
Mid-March |
Submit a Job Analysis Questionnaire Form (JAQ) to the
Human Resources office for all new staff positions
approved by the Budget Committee. |
| |
| Late March |
FY 09 Merit Recommendation Form due to Budget Office. |
| |
APRIL
|
| April |
Budget entered into automated Budget Development Module
(BDM) in PeopleSoft. |
| |
| Mid-April |
Faculty Evaluation Forms due to
Provost. |
| |
| Late April |
FY 09 Budget Megabud Reports sent to Departments for
verification |
|
|
MAY
|
| Early May |
Final Executive Summary of Budget due to System Budget
Office. |
| |
| 19-May |
Plans and budget materials due to System. |
| |
| 26-May |
Campus Budget Hearing with Chancellor. |
| |
JUNE
|
| 2-Jun |
LAR Process starts. |
| |
|
JULY
|
| July |
LAR Process |
| |
AUGUST
|
| 6-Aug |
Board of Regents Committee meeting to consider FY 09
Plan and Budget. |
| Early August |
Budget Committee meets with UHV faculty and staff to
present budget and annual plan. |
| |
| Mid-August |
Submit unit plan to Institutional Research office. |
| |
| 21-Aug |
Board of Regents meeting to consider FY 09 Plan and
Budget. |